US ROUTE 7 SHELBURNE-SOUTH BURLINGTON, VT SIGNALS UPGRADE
TRAFFIC IMPACT: Motorists should expect traffic control present with lane closures within the work areas
CONSTRUCTION ACTIVITIES:
The following is the anticipated work schedule for the week beginning Monday, July 12, 2021
Monday through Thursday 7:00 p.m. to 6:00 a.m.
- Continue pouring concrete for the mast pole foundations throughout the project limits
- General cleanup throughout the project
PROJECT TYPE: Signal upgrade
LOCATION: US Route 7, from McIntosh Avenue north to Swift Street. The six intersections include McIntosh Avenue, Baldwin Avenue, Laurel Hill Road, Brewer Parkway, Queen City Park Road and Swift Street.
PROJECTED COMPLETION: November 2021
SPECIAL CIRCUMSTANCES/NOTICES: Please email sbarrett@coibsinc.com, reference US Route 7 Signals, if you would like to receive weekly project updates via email.
Contact Information:
Name - Stephanie Barrett - Public Information Consultant
Phone - 802-399-7847
Email - sbarrett@coibsinc.com